Critical Path Method

Overview
This activity will enable you to do a network diagram for a project, identify the critical path and establish any slack time..

Activity Description
The weblink takes you to a video demonstrating how to identify the critical path on a network diagram.  Use this tutorials to complete Figure 3 below.  Figure 1 shows you the details of the activity, and Figure 2 shows the precedence diagram.  In the first instance, do a ‘forward pass’ on Figure 3 in order to establish how long the project will take.  Then do a ‘backward pass’ in order to identify any slack time in the project.
Figure 1:  Details of the Activity

Activity

Predecessor

Duration

A

 

2

B

A

5

C

 

3

D

A, C

4

E

B, D

7

F

E

4

G

D, F

5

H

E

6

I

G, H

3

Figure 2: Precedence Diagram


Figure 3: Worksheet to identify critical path and slack time

Websites
Use forward and backward pass…: https://www.youtube.com/watch?v=4oDLMs11Exs