Skip to main content
United States
Jump To
Support
Register or Log In
Support
Register or Log In
Instructors
Browse Products
Getting Started
Students
Browse Products
Getting Started
Return to Introduction to Accounting 2e Student Resources
Chapter 13 Self-test questions
Standard costing and variance analysis
Quiz Content
*
not completed
.
Which one of the following will not form part of the variable overheads variance calculations?
The number of hours it takes to produce products.
correct
incorrect
Actual variable overhead incurred during the accounting period.
correct
incorrect
Actual hours worked by employees during the accounting period.
correct
incorrect
Standard cost of direct labour.
correct
incorrect
*
not completed
.
Which of the following are limitations of standard costing? Please select all that apply.
Variance analysis information can be extensive and management may be overwhelmed by the volume of data presented to them.
correct
incorrect
Standard costing systems are rigid and inflexible.
correct
incorrect
Standard costing systems are too basic and simplistic to deliver any meaningful information.
correct
incorrect
Constant changes in costs and the need to update these makes standard costing systems time consuming to operate.
correct
incorrect
*
not completed
.
Sales price variance = (actual sales in units – budgeted sales in units) x standard contribution per unit.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
The direct material price variance shows how much of the total direct material variance is due to higher or lower usage of direct material in the actual production achieved.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
The budgets for product A indicate a fixed overhead allocation per unit of production of £6 and a variable overhead per unit of production of £8 based on a budget of 2,000 units per month production. During April, 2,500 units of product A were produced incurring £13,000 fixed overhead and £19,000 of variable overhead. What was the fixed overhead expenditure variance for April?
£1,000 Unfavourable
correct
incorrect
£1,000 Favourable
correct
incorrect
£2,000 Favourable
correct
incorrect
£3,000 Unfavourable
correct
incorrect
*
not completed
.
Product A is expected to use 5 metres of material at a standard cost of £5 per metre. In June, 2,700 metres of material were used to produce 600 products. The total cost of material in June was £16,200. What is the direct material price variance if budgeted production for June was 575 product As?
£625 Favourable
correct
incorrect
£1,200 Unfavourable
correct
incorrect
£1,500 Favourable
correct
incorrect
£2,700 Unfavourable
correct
incorrect
*
not completed
.
How are standard costs calculated and derived? Please select all that apply.
Standard costing recognizes that goods and services are made up of a fixed set of inputs.
correct
incorrect
The standard costs and revenues of a product or service represent the actual costs and revenues associated with each product or service.
correct
incorrect
The accuracy of each standard cost is improved over time through variance analysis of differences between the actual and standard costs and revenues of a product or service.
correct
incorrect
Standard costs are derived from numerous observations of an activity over time.
correct
incorrect
*
not completed
.
(Standard hours for actual production – actual hours for actual production) x standard rate per hour = direct_____________ variance.
Your response
*
not completed
.
Standard costing involves actual costs and revenues associated with a product or service.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
Which of the following factors would explain an unfavourable direct labour efficiency variance? Please select all that apply.
A higher rate of pay for production employees.
correct
incorrect
A reduction in training of production employees in the handling of materials.
correct
incorrect
A higher selling price for goods produced.
correct
incorrect
Lower quality material used in the production of goods.
correct
incorrect
*
not completed
.
CBB Limited uses a standard costing system for all its products. Product A has a standard selling price of £50 and budgeted total sales for the year ended 31 August 2021 of 5,000 units. The actual selling price for Product A throughout the year to 31 August 2021 was £48 and the actual units sold were 5,100. The actual variable cost of Product A amounted to £32 per unit in the year to 31 August 2021 while the standard variable cost of Product A is £33. Based on these actual and standard costs and revenues, what is the sales volume variance for Product A for the year ended 31 August 2021?
£1,500 Favourable
correct
incorrect
£1,600 Favourable
correct
incorrect
£1,700 Favourable
correct
incorrect
£1,800 Favourable
correct
incorrect
*
not completed
.
ZTC Limited's standard costing system shows that each jacket has a standard input material requirement of 4 metres of cloth. Cloth has a standard cost of £2.00 per metre. During July, budgeted production of jackets was 1,000. However, due to additional demand, 1,200 jackets were produced, using a total of 4,950 metres of cloth at a total cost of £9,360. What was ZTC Limited's direct material usage variance for the month of July?
£240 Favourable
correct
incorrect
£300 Unfavourable
correct
incorrect
£540 Favourable
correct
incorrect
£1,360 Unfavourable
correct
incorrect
*
not completed
.
PDT Limited uses a standard costing system. PDT Limited produces concrete slabs. The standard labour time for one concrete slab is 15 minutes. Direct labour is paid at the rate of £15 per hour. The company budgeted to produce 3,200 concrete slabs in March. Actual production for March was 3,400 concrete slabs. 835 labour hours were paid in March at a total cost of £12,692. What is the direct labour rate variance for concrete slabs for March?
£58 Favourable
correct
incorrect
£167 Unfavourable
correct
incorrect
£225 Favourable
correct
incorrect
£750 Unfavourable
correct
incorrect
*
not completed
.
PDT Limited uses a standard costing system. PDT Limited produces concrete slabs. The standard labour time for one concrete slab is 15 minutes. Direct labour is paid at the rate of £15 per hour. The company's budgeted production for March was 3,200 concrete slabs. Actual production for March was 3,400 concrete slabs. 835 labour hours were paid in March. Variable overhead is allocated to concrete slabs at the standard rate of £5.00 per labour hour and the actual variable overhead cost for March was £4,105. What is the variable overhead expenditure variance for concrete slabs for March?
£70 Favourable
correct
incorrect
£75 Favourable
correct
incorrect
£145 Favourable
correct
incorrect
£250 Favourable
correct
incorrect
*
not completed
.
TVT Limited uses a standard costing system. TVT Limited produces kitchen worktops in standard 6 metre lengths. The standard labour time for one kitchen worktop is 2 hours. Direct labour is paid at the rate of £18 per hour. The company's budgeted production of kitchen worktops in May was 4,000. Actual production for May was 3,800 kitchen worktops. 7,550 labour hours were paid in May at a total cost of £135,145. What is the direct labour total variance for kitchen worktops for May?
£755 Favourable
correct
incorrect
£900 Favourable
correct
incorrect
£1,655 Favourable
correct
incorrect
£3,600 Favourable
correct
incorrect
Previous Question
Submit Quiz
Next Question
Reset
Exit Quiz
Review all Questions
Submit Quiz
Are you sure?
You have some unanswered questions. Do you really want to submit?
Back to top
Printed from , all rights reserved. © Oxford University Press, 2025
Select your Country