Skip to main content
United States
Jump To
Support
Register or Log In
Support
Register or Log In
Instructors
Browse Products
Getting Started
Students
Browse Products
Getting Started
Return to Poole's Textbook on Contract Law 15e Student Resources
Self-test questions
Quiz Content
*
not completed
.
A breach of contract occurs when the time for performing a duty under the contract arrives and that duty is not performed. Which
one
of the following statements
most accurately
describes the legal consequence of a breach of contract?
Every breach of contract makes the contract-breaker liable to pay damages to the non-breaching party.
correct
incorrect
Every breach of contract entitles the non-breaching party to terminate the contract.
correct
incorrect
A breach of contract can automatically bring the contract to an end.
correct
incorrect
The contract-breaker is not liable to pay damages if the non-breaching party sustains no loss from the breach.
correct
incorrect
*
not completed
.
Difference in value damages are usually calculated on the basis of the 'market price' rule. In which
one
of the following situations does that rule apply? Assume all contracts are commercial/B2B contracts.
Under a contract for sale of goods, the buyer accepts the slightly defective goods and claims damages in respect of the minor defects.
correct
incorrect
Under a contract for sale of goods, the goods are acquired for the purpose of manufacturing machinery and are delivered late. The buyer accepts the goods and claims damages for the profits lost during the period when the machinery should have been in operation.
correct
incorrect
Under a contract for the sale of goods, the goods for sale are two sports cars tailor-manufactured for the buyer.
correct
incorrect
Under a contract for sale of goods, the buyer accepts the slightly delayed goods, resells them to a third party, and then claims damages for breach of contract.
correct
incorrect
*
not completed
.
Which of the following statements in relation to the 'cost of cure' measure of damages in breach of contract cases are
true
? [Please select
all
that apply.]
Cost of cure is measured by the loss of 'subjective benefits', i.e. 'consumer surplus', resulting from the breach of contract.
correct
incorrect
Cost of cure is normally unavailable where the contractual obligation breached is a qualified obligation to use reasonable care and skill.
correct
incorrect
Cost of cure is awarded irrespective of whether the non-breaching party intends to cure.
correct
incorrect
Cost of cure is available only when it is not out of all proportion to the non-breaching party's loss resulting from the breach.
correct
incorrect
*
not completed
.
Which
one
of the following statements concerning the recoverability of reliance loss is
true
?
Reliance loss must be claimed where it is difficult to prove expectation loss under the contract.
correct
incorrect
Reliance loss must be claimed where expectation loss relates only to a loss of a chance of making a profit.
correct
incorrect
The non-breaching party may recover both reliance loss and the net profit expected under the contract at the same time.
correct
incorrect
The non-breaching party may freely choose to recover reliance loss where reliance loss is higher than expectation loss.
correct
incorrect
*
not completed
.
Which of the following statements concerning the time for assessing damages are
true
? [Please select
all
that apply.]
Damages are generally assessed at the time of breach, which usually occurs at the time when performance becomes due.
correct
incorrect
The time for assessing damages may be postponed to a time subsequent to the time for performance.
correct
incorrect
Where damages are awarded in lieu of specific performance, damages are assessed at the date on which specific performance becomes impossible.
correct
incorrect
Damages may not be reduced where subsequent events occur which were known to the court at the date of the hearing and which have reduced the actual loss.
correct
incorrect
*
not completed
.
A agrees to repair B's broken mill shaft and to return it to B within a week. At the time of contracting, B points out that he has no spare mill shaft and that he will not be able to operate his mill until the repaired one has been returned. A does not return the repaired shaft until two weeks later. B sues A for breach of contract, claiming damages for the loss of profit during the second week, when his mill was closed as a result of A's delay. A argues that the damages claimed by B are too remote to be recoverable. In considering the approach taken in
Hadley
v
Baxendale
(1854) 9 Ex 341, which
one
of the following statements concerning A's argument is
true
?
The damages claimed by B are not too remote, because his loss of profit is a natural or normal loss resulting from A's breach of contract.
correct
incorrect
The damages claimed by B are too remote, because his loss of profit is an abnormal loss resulting from A's breach of contract.
correct
incorrect
The damages claimed by B are too remote, because his loss of profit is not within the reasonable contemplation of the parties at the time of contracting.
correct
incorrect
The damages claimed by B are not too remote, because his loss of profit is an abnormal loss within the parties' actual knowledge at the time of contracting.
correct
incorrect
*
not completed
.
Which of the following statements are consistent with the decision in
Farley
v
Skinner (No. 2)
[2001] UKHL 49, [2002] 2 AC 732? [Please select
all
that apply.]
Non-pecuniary loss may be recovered as damages for a breach of contract if it is consequent on physical inconvenience caused by the breach.
correct
incorrect
Non-pecuniary loss may be recovered as damages for a breach of contract only if the very object of the contract is to provide pleasure, relaxation, or peace of mind.
correct
incorrect
Non-pecuniary loss is generally not recoverable as damages for a breach of contract if the breach relates to a qualified contractual obligation to use reasonable care and skill.
correct
incorrect
Non-pecuniary loss may be recovered as damages for a breach of contract if the major or important object of the contract is to provide pleasure, relaxation, or peace of mind.
correct
incorrect
*
not completed
.
Which of the following statements concerning duty of mitigation following a breach of contract are
true
? [Please select
all
that apply.]
The non-breaching party will itself be in breach of contract if it fails to take reasonable steps to avoid the loss flowing from the breach.
correct
incorrect
If the non-breaching party takes reasonable steps to avoid, and successfully wipes out, the loss flowing from the breach, it will be entitled to only nominal damages for that breach.
correct
incorrect
If the non-breaching party takes reasonable steps in an attempt to avoid the loss flowing from the breach and these reasonable steps result in increased loss, it will not be entitled to recover that increased loss.
correct
incorrect
In the case of anticipatory repudiatory breach, where the non-breaching party accepts the breach as terminating the contract, loss sustained is subject to the mitigation principle from the moment of that acceptance
correct
incorrect
*
not completed
.
A and B enter a contact whereby A is to supply 20 tons of coal per month to B's factory at £300 per ton, by the third day of each month, until either side gives one month's notice to terminate this agreement. At the time of contracting, A knows that B relies on the coal to keep his factory operating. The contract stipulates that, if A is late in delivering a particular month's consignment, he will pay to B 'by way of compensation, a sum of £75 for each full day by which delivery is delayed'. A is eight days late in delivering the February consignment and, as a result, B suffers a loss of £1,000. B claims damages for this loss. Which
one
of the following statements
most accurately
describes the position between A and B?
B is not entitled to £1,000 as damages, because the compensation clause in the contract is a liquidated damages clause and precludes B from claiming his actual loss.
correct
incorrect
B is entitled to £1,000 as damages, because the compensation clause in the contract is a penalty clause and is thus wholly unenforceable and B's actual loss is not too remote to be recoverable.
correct
incorrect
B is not entitled to £1,000 as damages, because this loss is too remote to be recoverable.
correct
incorrect
B is entitled to £1,000 as damages, because B is entitled to claim his actual loss where it is greater than the stipulated sum in the contract.
correct
incorrect
*
not completed
.
A Ltd, a telecommunications service provider, intends to purchase a country house for its new headquarters. It employs B to conduct a survey of a particular property, emphasising the need to look out for any localised traffic problems. B, in breach of contract, fails to discover that there is a notorious traffic blackspot very close to the country house. A Ltd's staff and clients experience appalling traffic congestion in order to get on and off site. Which
one
of the following damages claims has the most chance of succeeding, on the basis of the above facts?
A Ltd claims damages for the physical inconvenience suffered by its staff in commuting to and from work.
correct
incorrect
A Ltd claims damages for the reduced productivity of its business.
correct
incorrect
A Ltd claims damages for loss of reputation as a result of the traffic problem.
correct
incorrect
A Ltd claims damages for the disappointment of not being able to locate its headquarters in a country house free from such serious traffic problems.
correct
incorrect
*
not completed
.
According to the compensation principle, the non-breaching party is normally entitled to recover as loss of profit any profit made from the breach by the contract-breaker.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
The purpose of awarding contractual damages is generally to put the non-breaching party into the position it would have been in had the contract been performed as agreed.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
Under a contract for the sale of goods, where the buyer unreasonably refuses to accept the goods and the seller resells the goods to a third party at the contract price, the seller is entitled to claim damages for loss of profit if market supply of the goods in general is greater than demand.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
It was established in
Ruxley Electronics and Construction Ltd
v
Forsyth
[1996] 1 AC 344 that 'cost of cure' damages are generally not available where there is no difference in value between the actual performance and the contract performance.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
In general, the test of remoteness of damages in contract is stricter than the test of remoteness of damages in tort.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
In order to recover damages for a breach of contract, the non-breaching party must show that the breach is the only effective cause of its loss.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
Where loss is caused by a breach of a strict contractual obligation and by the contributory negligence of the non-breaching party, the damages payable by the contract-breaker cannot be reduced proportionately according to the provisions of the Law Reform (Contributory Negligence) Act 1945.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
According to
Ruxley Electronics and Construction Ltd
v
Forsyth
[1996] 1 AC 344, non-pecuniary loss is generally recoverable where cost of cure damages are not available.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
It is well established that a wrongfully dismissed employee may claim damages for financial loss caused by difficulty in obtaining alternative employment as a result of the manner of the dismissal.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
In
Makdessi
v
Cavendish Square Holding BV
[2015] UKSC 67, [2015] 3 WLR 1373, the Supreme Court stated that the scope of the penalty rule applies in circumstances concerning agreed damages clauses that are payable on breach and is not concerned with payments concerning primary contractual obligations.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
Where part of the contract price is paid in advance as a deposit, the payment is normally not recoverable in the event of breach of the contract by the payor, even if the payee has not suffered any loss as a result of the breach.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
Following the decision of the House of Lords in
Transfield Shipping Inc.
v
Mercator Shipping Inc., The Achilleas
[2008] UKHL 48, [2009] 1 AC 61, the courts have dispensed with the traditional approach of assessing remoteness of damages under the rules of
Hadley v Baxendale
(1854) 9 Ex 341 and instead adopt an approach based on whether one party 'assumed responsibility' for the losses of the other party.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
A is setting up a launderette business, opening to the public next Tuesday. He agrees to purchase from B six new washing machines at a price of £1,500 each, to be delivered and installed next Monday. B knows that A has advertised the opening of his launderette for Tuesday. On the Monday, B telephones A and says that she will be unable to deliver the machines until the following week. A immediately contacts other suppliers and receives the following offers. X offers to deliver and install higher quality washing machines by Monday evening, at a price of £2,000 each. Y offers a price of £1,250 per machine, provided A can arrange delivery (the machines can be picked up immediately). Which
one
of the following statements is consistent with A's duty of mitigation?
A is required by the mitigation principle to take Y's offer.
correct
incorrect
A may take X's offer and then claim damages from B.
correct
incorrect
A is required by the mitigation principle to wait for B's delivery because it is unreasonable for A to take either X's or Y's offer.
correct
incorrect
A may not take X's offer because the price asked for is too high.
correct
incorrect
*
not completed
.
A, the owner of a vessel, enters into an agreement with a charterer, B, for the charter of the vessel. A spends money preparing the vessel before B subsequently, in breach of contract, repudiates the agreement. However, A is then immediately able to enter into a new agreement with another charterer, C, and due to an upturn in the market rate, receives a much greater profit than that which she would have received under the agreement with B. Regardless of the greater profit received, A will always be entitled to recover the wasted expenditure in reliance on the agreement with B.
True
correct
incorrect
False
correct
incorrect
*
not completed
.
A Ltd enters into a construction contract with B Ltd under which A is to build a warehouse for B for £200,000. The estimated total cost for A to complete the building work at the time of the contract is £160,000. Due to market changes, however, the estimated total cost of completing the work becomes £220,000 before A starts building. B then fails to make some prepayments, which entitles A to terminate the contract. A terminates the contract and claims for damages, amounting to £50,000, as wasted expenses incurred in preparation for the building work. Which
one
of the following statements
most accurately
summarises the legal position between the two parties?
A is entitled to an award of £50,000 because this reflects expenses incurred for the purpose of performing the contract.
correct
incorrect
A is entitled to an award of £40,000 because this reflects A's net profit under the contract at the time of making the contract.
correct
incorrect
A is entitled to £30,000 because this reflects expenses that would have been recouped had the contract been duly performed.
correct
incorrect
A is entitled to nominal damages only because A would not have made a net profit had the contract been duly performed.
correct
incorrect
Previous Question
Submit Quiz
Next Question
Reset
Exit Quiz
Review all Questions
Submit Quiz
Are you sure?
You have some unanswered questions. Do you really want to submit?
Back to top
Printed from , all rights reserved. © Oxford University Press, 2024
Select your Country