Process costing

Quiz Content

not completed
. During December, 25,000 litres of materials were input to CIC Limited's paint making process at a cost of £55,000. Conversion costs for the month were £14,000. 20,000 litres of paint were completed during December and were transferred to finished goods. The work in progress at the end of December was 60% complete with respect to both materials and conversion costs. What is the monetary value of work in progress at the end of December in CIC Limited's paint making process?

not completed
. During September, VVF Limited used 18,000 litres of input material in its detergent making process at a cost of £52,000. Conversion costs for the month totalled up to £12,800. Finished production of detergent during September was 15,000 litres. 3,000 litres of work in progress on 30th September were 40% complete with respect to both materials and conversion costs. What is the value of the work in progress at the end of September in VVF's detergent making process?

not completed
. AVA Limited's glue making process in March turned 10,000 litres of input materials into 8,000 litres of finished production with a total process cost of £108,000 and 2,000 litres of closing work in progress with a cost of £10,800. What was the % completion of work in progress at the end of March?

not completed
. BJJ Limited's solvent making process produced 16,000 units of completed production in August. At the end of August, there were 4,000 units of work in progress which were 75% complete with respect to materials and 40% complete with respect to conversion costs. 20,000 litres of materials were put into the process in August at a cost of £76,000. Conversion costs for the month totalled up to £26,400. What is the value of work in progress at the end of August?

not completed
. TTP Limited's paint production process produced 9,000 litres of finished paint production in October. At the end of October, there were 3,000 litres of work in progress which were 60% complete with respect to materials and 50% complete with respect to conversion (labour and overhead) costs. Materials input to the paint making process in October had a cost of £70,200 while conversion (labour and overhead) costs for the month were £30,240. What is the equivalent unit cost that will be used in valuing finished goods and closing work in progress for October?