Chapter 7 Self-test questions

Chapter 7 Self-test questions

Remedies for breach of contract

Quiz Content

not completed
. According to the compensation principle, the non-breaching party is normally entitled to recover as loss of profit any profit made from the breach by the contract-breaker.

not completed
. The purpose of awarding contractual damages is generally to put the non-breaching party into the position it would have been in had the contract been performed as agreed.

not completed
. Which of the following statements in relation to the 'cost of cure' (or cost of repair) measure of damages in breach of contract cases are true? [Please select all that apply.]

not completed
. A Ltd enters into a construction contract with B Ltd under which A is to build a warehouse for B for £200,000. The estimated total cost for A to complete the building work at the time of the contract is £160,000. Due to market changes, however, the estimated total cost of completing the work becomes £220,000 before A starts building. B then fails to make some prepayments, which entitles A to terminate the contract. A terminates the contract and claims for damages, amounting to £50,000, as wasted expenses incurred in preparation for the building work. Which one of the following statements most accurately summarises the legal position between the two parties?

not completed
. A, the owner of a vessel, enters into an agreement with a charterer, B, for the charter of the vessel. A spends money preparing the vessel before B subsequently, in breach of contract, repudiates the agreement. However, A is then immediately able to enter into a new agreement with another charterer, C, and due to an upturn in the market rate, receives a much greater profit than that which he would have received under the agreement with B.
Regardless of the greater profit received, A will always be entitled to recover the wasted expenditure in reliance on the agreement with B.

not completed
. A agrees to repair B's broken mill shaft and to return it to B within a week. At the time of contracting, B points out that he has no spare mill shaft and that he will not be able to operate his mill until the repaired one has been returned. A does not return the repaired shaft until two weeks later. B sues A for breach of contract, claiming damages for the loss of profit during the second week, when his mill was closed as a result of A's delay. A argues that the damages claimed by B are too remote to be recoverable. Which one of the following statements concerning A's argument is true?

not completed
. Which of the following statements are consistent with the decision in Farley v Skinner (No. 2) [2001] UKHL 49, [2002] 2 AC 732? [Please select all that apply.]

not completed
. Where loss is caused by a breach of a strict contractual obligation and by the contributory negligence of the non-breaching party, the damages payable by the contract-breaker cannot be reduced proportionately according to the provisions of the Law Reform (Contributory Negligence) Act 1945.

not completed
. A and B enter a contact whereby A is to supply 20 tons of coal per month to B's factory at £300 per ton, by the third day of each month, until either side gives one month's notice to terminate this agreement. At the time of contracting, A knows that B relies on the coal to keep his factory operating. The contract stipulates that, if A is late in delivering a particular month's consignment, he will pay to B 'by way of compensation, a sum of £75 for each full day by which delivery is delayed'. A is eight days late in delivering the February consignment and, as a result, B suffers a loss of £1,000. B claims damages for this loss. Which one of the following statements most accurately describes the position between A and B?

not completed
. In Makdessi v Cavendish Square Holding BV [2015] UKSC 67, [2015] 3 WLR 1373, the Supreme Court stated that the scope of the penalty rule applies in circumstances concerning agreed damages clauses that are payable on breach and is not concerned with payments concerning primary contractual obligations.

Back to top